Nearly There...
- nigghallsteering
- Apr 15, 2025
- 1 min read
The Nigg Community Hall Steering Group have submitted the KLTR application ahead of the deadline to reclaim the hall into community ownership.
What happens next?
By 16th April 2025 – submit application to the KLTR. Then the following activities will commence.
Application to the Scottish Land Fund (stage 2) for funding to cover legal fees and additional revenue costs associated with the transfer of ownership. Submit by 9th June 2025.
13th May – OPTS advisory panel of six independent panellists meet to assess NCHSG KLTR application.
20th May - Chair of panel will send report to KLTR
End May 2025 - NCHSG will receive letter of decision from KLTR
June 2025 – Conveyancing and transfer. During which time the NCHSG will complete the following activities:
Empower and engage community through focus groups to develop a vision for hall and inform funding applications.
Complete applications to capital funds as listed in appendix 3.
Continue community engagement to grow membership and develop vision for the phased development.
September 2025 – anticipated date of conclusion of transfer.